Royal Boskalis, Aberdeen Offshore Wind Farm (AOWF)
Two-phase onshore and offshore support package for the Aberdeen Offshore Wind Farm, covering project management, rope access, equipment installation and post-installation remedial works. All scopes completed with zero LTIs.
- Cliente
- Royal Boskalis
- Industria
- offshore
- Ubicación
- Aberdeen Offshore Wind Farm, North Sea, UK
- Fecha del Proyecto
- agosto de 2023
El Desafío
The Aberdeen Offshore Wind Farm scope required a coordinated package of onshore preparation works and offshore remedial activities across multiple mono-piles in the northern sector of the North Sea.
Delivering both phases safely required tight planning around marine logistics, weather windows and rope access execution at height, with no tolerance for lost-time incidents on a high-visibility renewables project.
Nuestra Solución
During the onshore phase at LNG Quay Peterhead, our team provided project management, rope access services, installation of the RTK container, survey equipment and suction pumps, and preparation of the mono-piles ahead of marine deployment.
The offshore phase covered remedial works including repair of damaged coatings, removal of installation equipment and post-installation electrical work, executed in line with the client's safety and quality requirements.
Resultados
All work across both the onshore and offshore scopes was completed in a safe and controlled manner with zero Lost Time Injuries (LTIs).
0
Lost Time Injuries
2
Project phases delivered